AY Line – Main Gravitational Sewage Transmission Line
Dan Region - Central Israel
Background
AY Line Main Gravitational Sewage Transmission Line is a part of AY Line Project – The third Main Transmission Line of Dan Region, that servs a population of 2,000,000.
The project was performed under Ayalon Highway (North) using Microtunneling technology in presence of groundwater without interfering the heavy traffic of the highway above.
AY Line is a part of AY Line Project. More information about this project could be found here:
- AY Line Project
- Ayalon Sewage Pumping Station
- AYM Line – Main Sewage Raising Main Line
- AYQ Line – Main Sewage Raising Main Line
Balasha-Jalon provided the general design, engineering coordination, detailed designs. and also provided general supervision on site.
Basic Design Data
Line length
7,500
m
Pipe diameter
1,600
mm
Depth
6 - 26
m
Material of the Pipe
Reinforced concrete
Project Technology
Microtunneling