Basic Design Data
Average Design Flow
6,000
m3/day
Average B.O.D. Load
2,400
Kg/day
Effluent Quality
15/20/15
BOD/TSS/N
Liquid Process and Facilities
Main Process
B.N.R. Activated Sludge without primary clarifiers
Facilities
- Bar screens
- Grit removal
- B.N.R. Activated sludge reactors with diffused aeration system
- Final clarifiers
Sludge Process and Facilities
Main Process
Aerobic Stabilization
Facilities
- Sludge tanks
- Drum thickeners for W.A.S. thickening
- Aerobic sludge digesters with diffused air system
- Decanter centrifuges for the dewatering of the stabilized sludge